SECTION 1. Chapter 1.5 (commencing with Section 21010) is added to Division 13 of the Public Resources Code, to read:

CHAPTER 1.5. BUILDING AN AFFORDABLE CALIFORNIA ACT

ARTICLE 1. Title, Findings and Declarations, Purpose.

21010. Title.

21011. Findings and Declarations.

The People of the State of California hereby find and declare the following:

(a) California's outdated system for approving essential projects is too slow, too bureaucratic, and too costly. Essential projects like clean water, clean energy, hospitals, affordable housing, roads, wildfire prevention, schools, public safety, and other infrastructure improvements are being delayed or blocked by unnecessary red tape, bureaucratic delays, and excessive lawsuits.

(b) These delays substantially increase the cost of living for all Californians. Research shows that permitting delays alone add tens of thousands of dollars to the price of a new home—driving up rents and mortgages for homeowners and renters. Similar red tape adds billions of dollars to the cost of building hospitals, water infrastructure, roads, bridges, clean energy, schools, broadband, and wildfire mitigation projects—costs ultimately passed on to consumers and taxpayers.

(c) California's permitting laws were written more than 50 years ago, before today's modern environmental laws were in place. That outdated system now works against the state's environmental and public health goals by slowing down or blocking essential projects that would reduce air pollution, lower greenhouse gas emissions, safeguard water supplies, protect communities from wildfire, and preserve wildlife and the environment.

(d) The Building an Affordable California Act will modernize and streamline state law to cut bureaucratic red tape and unnecessary delays; limit frivolous lawsuits that block essential projects while allowing public agencies and essential project applicants to continue sharing the burden of defending against such suits; and speed up delivery of projects Californians rely on every day.

(e) Every year of delay means Californians wait longer and pay more for the things they need most. The Building an Affordable California Act applies to the state's most essential projects, including:

(1) Clean drinking water and secure water supplies for communities across the state.

(2) Safe, modern hospitals and clinics to ensure access to affordable health care.

(3) Clean energy and reliable electricity to reduce energy bills and fight climate change.

(4) Housing of all types in order to make housing more affordable for families struggling with skyrocketing rents and mortgages as well as vulnerable senior populations.

(5) Roads, bridges, and transit to cut traffic congestion and improve public safety.

(6) Wildfire prevention and resilience projects to protect lives, homes, and natural resources.

(7) Safe, modernized public schools and educational facilities for students and educators.

(8) Broadband and telecommunications infrastructure to connect underserved communities and expand opportunity.

(f) By speeding up these essential projects, the Building an Affordable California Act will make California more affordable and lower the cost of housing, energy, electricity, health care, and other necessities, while also reducing taxpayer costs for public works projects.

(g) The Building an Affordable California Act will also jump-start projects that create well-paying jobs and put tens of thousands of Californians to work—especially in construction, clean energy, and infrastructure—helping grow California's economy when it is needed most.

(h) Importantly, the Building an Affordable California Act maintains state and federal clean air, clean water, and environmental protection laws such as the Endangered Species Act, the Safe Drinking Water Act, the Toxic Substances Control Act, the Clean Water Act, the Clean Air Act, the Environmental Quality Improvement Act, the Global Warming Solutions Act, the California Coastal Act, and the Resource Conservation and Recovery Act. This chapter will help build the projects needed to make California more affordable—without repealing these laws that keep families and the environment safe.

(i) We can and must build an affordable California.

21012. Statement of Purpose.

The purpose of this chapter is to make California more affordable by streamlining and speeding approval of essential projects—reducing costs for families and taxpayers, improving quality of life, creating good jobs, and maintaining California's strongest-in-the-world environmental protections.

ARTICLE 2. Application of Chapter and Interaction with Other Laws.

21013. Projects Subject to this Chapter.

21014. Application of Chapter.

(a) This chapter does not diminish the authority of any public agency to approve or disapprove an essential project. No outcomes on any proposed essential project are preordained by this chapter.

(b) This chapter does not exempt any essential project from environmental review under this division or any other law. Instead, this chapter establishes clear timelines and other procedures for review under this division and administrative permit review for essential projects.

(c) Except as otherwise provided herein, this chapter shall apply to review and processing of any and every application or approval for an essential project and its accompanying land use entitlements, including without limitation, discretionary adjudicative and legislative land use entitlements triggering programmatic, plan-level, or project-level environmental review under this division.

(d) This chapter shall apply to all public agencies.

(g) The timelines and deadlines set forth in this chapter shall apply to all essential project applications that are determined or deemed complete, pursuant to Section 21017 or any other law, after the effective date of this chapter irrespective of the date of the application's submission.

(i) Nothing in this chapter prohibits a public agency from imposing a fee upon an applicant, consistent with Article XIII A and Article XIII C of the California Constitution, for purposes of covering governmental costs associated with processing and reviewing essential project applications.

(j) An applicant may consent to providing a public agency with additional time to complete environmental review pursuant to Sections 21018 or 21019, or to make a decision on other public agency action sought by the applicant pursuant to Section 21023, by agreeing to withhold a written request that the applicant is otherwise entitled to submit pursuant to subdivision (a) of Section 21020 or subdivision (b) of Section 21023.

21015. Interaction with Other Laws.

(b) To the extent that an ambiguity arises regarding how this chapter might operate in conjunction with other provisions of law, the policies and intent set forth in Section 21029 shall be controlling.

ARTICLE 3. Initial Screening, Tribal Consultation, and Completeness of Essential Project Applications.

21016. Tribal Cultural Resources: Initial Screening and Tribal Consultation on Essential Projects.

(a) Purpose. The People of the State of California hereby declare that this section is necessary in order to provide for early and meaningful tribal consultation as a key element of essential project planning while maintaining protections for tribal cultural resources. Consulting Tribes have knowledge and expertise concerning tribal cultural resources located within essential project areas.

(b) Construction and Interpretation.

(1) Notwithstanding Section 21015 or any other provision of law, the tribal consultation process for essential projects shall follow the provisions set forth in this section.

(2) Nothing in this chapter is intended to alter or conflict with federal government-to-government consultation obligations involving Consulting Tribes.

(3) The timelines established in Article 4 shall not alter the duration of consultation with a Consulting Tribe on an essential project pursuant to Sections 21080.3.1 and 21080.3.2.

(4) If any technical studies are conducted for the essential project that inform analysis, measures and/or treatment of tribal cultural resources, Consulting Tribes shall be afforded the opportunity to review and provide input on those studies.

(5) When provided by a Consulting Tribe, tribal traditional knowledge shall be incorporated in the identification, treatment, and protection measures concerning tribal cultural resources. As tribal cultural resources is a separate category from cultural resources and archaeological resources, some archaeological methods and standards may not be appropriate for tribal cultural resources. If the lead agency elects not to utilize tribal methods and standards or tribal traditional knowledge, it shall explain its decision in the environmental documents for the essential project, supported by substantial evidence.

(6) All information regarding tribal cultural resources and tribal traditional knowledge disclosed by a Consulting Tribe shall remain confidential consistent with subdivision (c) of Section 21082.3, and such information shall not be disclosed in the administrative record of proceedings without the permission of the Consulting Tribe. Lead agencies shall, in consultation with affected Consulting Tribes, determine appropriate measures to maintain confidentiality of information regarding tribal cultural resources and tribal traditional knowledge, including, but not limited to, redaction of precise locations, restricted mapping, secure data storage, or other protective handling of tribal cultural resources information. Any written explanation under paragraph (5) of subdivision (c) shall not be subject to challenge to the extent the lead agency does not have permission from the Consulting Tribe to disclose supporting information due to the confidentiality requirements of this paragraph.

(7) Completion of the initial screening process pursuant to subdivision (c) operates separately from, and does not modify, pause, or affect, any requirements or timelines set forth in Section 21017 or any other provisions of this division.

(d) Tribal consultation. Tribal consultation for an essential project shall be conducted pursuant to Sections 21074, 21080.3.1, 21080.3.2, 21082.3, 21084.2, and 21084.3, except as modified as follows:

(1) The purpose of tribal consultation is to identify tribal cultural resources and evaluate treatment and protection measures for those tribal cultural resources, including the implementation of treatment and protection measures.

(2) Tribal consultation is not meaningful if the Consulting Tribe is not provided with reasonably requested technical information, including, but not limited to, project information and constraints, data, maps, and information concerning project activities as they relate to treatment and protection of tribal cultural resources. During tribal consultation pursuant to this subdivision, the lead agency shall engage in iterative discussions with the Consulting Tribe regarding the development of mitigation measures related to tribal cultural resources, including preliminary concepts or approaches prior to publication of any draft environmental document. This includes notifying the Consulting Tribe of any existing technical studies or reports in the lead agency's possession that relate to tribal cultural resources on or in the vicinity of the essential project site, to the extent permitted by applicable confidentiality laws, and providing the Consulting Tribe with access to such studies or reports. To the extent any draft environmental review document is provided to the applicant for review in advance of the public comment period for that environmental review document, such draft shall also be made available to the Consulting Tribe at the time it is provided to the applicant. Nothing in this section shall be construed to require the lead agency to prepare or circulate draft environmental review documents for purposes of tribal consultation.

(3) Where the lead agency, a Consulting Tribe, and the applicant agree in writing to measures to avoid or mitigate a significant effect on a tribal cultural resource, those measures and any written agreement shall become enforceable conditions of project approval, subject to the confidentiality requirements under paragraph (6) of subdivision (b).

(e) Treatment and protection of tribal cultural resources. When feasible, damaging effects to any tribal cultural resources shall be avoided.

(1) Consistent with subdivision (b) of Section 21014, nothing in this subdivision alters the lead agency's obligation under CEQA to avoid or mitigate significant impacts to tribal cultural resources when feasible. Mitigation and treatment measures adopted in consultation with the Consulting Tribe pursuant to this subdivision to avoid or minimize significant impacts to tribal cultural resources shall be consistent with the following:

(A) Avoidance and preservation in place shall be considered when requested by the Consulting Tribe. A tribal cultural resource may be avoided or preserved in place through project design, buffering, or other protective measures to avoid the tribal cultural resources and protect the cultural and natural context, or planning greenspace, parks, or other open space to incorporate the tribal cultural resources with culturally appropriate protection and management criteria, which are referenced in the project's environmental documents.

(B) If an essential project has the potential to cause a substantial adverse change in the significance of a tribal cultural resource, and avoidance and preservation in place are not feasible, the lead agency shall demonstrate and document the basis for that determination with substantial evidence, and the Consulting Tribe may identify culturally appropriate mitigation measures, which the lead agency shall consider and incorporate, to the extent feasible, in developing mitigation and treatment measures in a manner consistent with paragraph (2) of subdivision (b) of Section 21084.3.

(C) When an essential project proposes construction-related ground disturbance activities and when requested by the Consulting Tribe, the lead agency shall include inadvertent discovery measures to reduce significant impacts to tribal cultural resources. Such measures may include procedures for temporary halts of grading, identification and assessment protocols, timing provisions, and additional treatment methods or protective measures.

(f) Essential project approval. A lead agency may only approve an essential project pursuant to this section when all of the following apply:

(1) Tribal consultation has concluded in good faith;

(2) Where there is agreement among all parties under either paragraph (4) of subdivision (c) or subdivision (d), any agreed-upon mitigation and avoidance measures are included as enforceable project conditions; and

(3) If avoidance and preservation in place is not feasible, the lead agency has demonstrated and documented the basis for that determination with substantial evidence and incorporated other measures to minimize impacts consistent with CEQA.

21017. Determining Completeness of Essential Project Applications.

ARTICLE 4. Review of Completed Applications for Essential Projects.

21018. Local Agency Timeline for Completing Environmental Review of Essential Projects.

21019. Timeline for Completing Environmental Review of Essential Projects by Public Agencies that are Not Local Agencies.

(a) A public agency other than a local agency that is acting as a lead agency ("non-local lead agency") for an essential project shall decide whether the project is subject to subdivision (b), subdivision (c), or subdivision (d) within 30 days of the earlier of the essential project application being determined or deemed to be complete pursuant to Section 21017, or deemed complete pursuant to any other law.

(b) Essential projects that require an environmental impact report. For essential projects that require an environmental impact report, the non-local lead agency shall make a final determination whether to certify an environmental impact report no later than 365 days after the earlier of the essential project application being determined or deemed to be complete pursuant to Section 21017, or deemed complete pursuant to any other law.

(c) Essential projects that require a negative declaration or mitigated negative declaration. For essential projects that require a negative declaration or mitigated negative declaration, the non-local lead agency shall make a final determination whether to adopt a negative declaration or mitigated negative declaration no later than 180 days after the earlier of the essential project application being determined or deemed to be complete pursuant to Section 21017, or deemed complete pursuant to any other law.

(d) For all other environmental review documentation prepared under this division or this chapter for an application or approval of an essential project, the non-local lead agency shall, within 90 days after the earlier of the essential project application being determined or deemed to be complete pursuant to Section 21017 or deemed complete pursuant to any other law, make a final determination that the essential project is exempt from this division or that the essential project's impacts were previously evaluated under a prior environmental review document pursuant to, without limitation, Section 21083.3 or Section 21094.5, or an addendum pursuant to Section 15162 or Section 15164 of the State CEQA Guidelines.

(e) The deadlines set forth in subdivision (b), subdivision (c), and subdivision (d) shall be extended upon written request from the applicant.

21020. Noncompliance with Timelines for Completing Environmental Review of Essential Projects.

21021. Timeline for Public Comments on Essential Projects.

21022. Determination of Impacts.

21023. Other Public Agency Actions for Essential Projects.

ARTICLE 5. Preliminary Scoping Process and Streamlined Alternatives Analysis for Essential Projects.

21024. Preliminary Scoping Process for Essential Projects.

(a) An applicant may, but is not required to, utilize the preliminary scoping process and streamlined alternatives analysis as provided in this article. However, where an applicant voluntarily chooses to utilize this preliminary scoping process and streamlined alternatives analysis, it shall comply with this article.

(b)(1) Prior to submitting an application for an essential project, an applicant that chooses to proceed in accordance with this article shall provide written notice to the lead agency of its intent to complete the scoping process and streamlined alternatives analysis set forth in this article.

(2) The written notice shall present a preliminary overview and description of the proposed essential project sufficient to inform the lead agency and the public of the anticipated features of the project. The written notice is not required to include detailed engineering plans, technical studies, or design-level drawings. The description shall include, to the extent known, the following:

(A) The project's location, size, and boundaries.

(B) The principal components and fundamental purpose of the project.

(C) The general type of land use, facility, or infrastructure proposed.

(D) Any known or reasonably foreseeable resource areas that may be impacted.

(E) Any anticipated permits or approvals required from public agencies.

(3) The written notice shall also prominently identify an email address for the applicant where the lead agency and the public may submit comments on the proposed essential project.

(c)(1) After receipt by the lead agency of the written notice described in subdivision (b), the applicant and the lead agency shall engage in at least two meetings for the purpose of discussing the proposed essential project, potential alternatives, and identifying potentially impacted resource areas.

(2) The lead agency shall maintain a record of all meeting summaries.

(e) An applicant may, but shall not be required to, convene one or more public meetings or workshops, including via virtual or online formats, for the purpose of obtaining additional public input on the proposed essential project.

(f) The preliminary scoping process described in this section shall be completed within not more than 60 days from the date that the lead agency received written notice pursuant to subdivision (b).

(g) Where an applicant does not elect to utilize the scoping process provided in this section, other scoping requirements set forth in this division shall continue to apply.

(h) Notwithstanding any provision of this section, with respect to an essential housing project, the preliminary scoping process provided herein shall not be a prerequisite to filing a preliminary application under the Housing Crisis Act of 2019 as enacted by Chapter 654 of the Statutes of 2019 (Senate Bill 330).

21025. Streamlined Alternatives Analysis for Essential Projects.

ARTICLE 6. Judicial Review of Essential Project Approvals or Authorizations.

21026. Judicial Review of Essential Project Approvals or Authorizations.

(d) Nothing in this article shall be construed to supersede Section 1756 and Section 1759 of the Public Utilities Code, or any other provision of law governing judicial review of orders or decisions of the Public Utilities Commission.

21027. Timelines and Processes Applicable to Judicial Review of Essential Project Approvals or Authorizations.

(b) Administrative Record.

The whole administrative record consists only of notices, studies, and other documents consistent with the following:

(1) Documents required under this division to be sent or distributed to members of the public by the lead agency, made available to the public at a public repository such as a library, or included on the website of the lead agency; and

(2) With respect to public comments, comments described in subdivision (d) of Section 21021, and responses and comments described in subdivision (e) of Section 21021.

(d) Subsequent Approvals or Authorizations.

(1) No further action or proceeding to challenge the implementation through completion of construction or subsequent approval or authorization of an essential project, or portion of an essential project, may be filed if the public agency's approval or authorization was not subject to a judicial challenge, the public agency approval or authorization was challenged and upheld, or the public agency has filed a return to the writ which has been accepted as satisfactory by the court pursuant to subdivision (c).

(2) Minor modifications to an essential project which do not result in any new significant impacts, or which do not substantially worsen any previously identified significant impacts, of the initially approved essential project, may not be challenged in an action or proceeding under this division.

ARTICLE 7. Definitions.

21028. Definitions.

For purposes of this chapter, as used in both the singular and plural form, the following definitions shall apply:

(a) "Applicant" means any person, legal entity, public agency, or public utility that proposes an essential project.

(b) "Approval or authorization" means any approval, authorization, determination, finding, financing, real property transaction or contract, or other public agency actions that further the advancement, construction, completion, or realization of an essential project.

(c) "California educational institution" means all of the following: a school district; a county superintendent of schools; a county board of education; a community college district; a state special school; the Board of Governors of the California Community Colleges or the Chancellor of the California Community Colleges; the California State University or the Board of Trustees of the California State University; the University of California or the Regents of the University of California; the University of California Law San Francisco (formerly Hastings College of the Law); a charter school established pursuant to Part 26.8 (commencing with Section 47600) of Division 4 of Title 2 of the Education Code; and a nonprofit college or university with membership in the Association of Independent California Colleges and Universities.

(d) "CEQA" means the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code).

(g) "Educational facility" means any real property, facility, structure, building, or fixture that is owned or operated, or will be owned or operated upon completion, by one or more California educational institutions for educational purposes.

(h) "Environmental review document" or "environmental review documentation" means initial studies; negative declarations; mitigated negative declarations; draft and final environmental impact reports; documents prepared as substitutes for environmental impact reports; negative declaration and mitigated negative declarations under a program certified pursuant to Section 21080.5; documents or documentation used to substantiate the applicability of statutory or categorial exemptions from this division or streamlining provisions that include, without limitation, those under Sections 21083.3 and 21094.4; addenda and other supplemental or subsequent review documents; documents prepared under the National Environmental Policy Act and used by a public agency in the place of any of the foregoing documents or documentation; and environmental documents as defined in Section 15361 of Title 14 of the California Code of Regulations.

(i)(1) "Essential broadband Internet access project" means a project to provide mass-market retail service by wire service, wireless service, or radio to customers in this state that provides the capability to transmit data to, and receive data from, all or substantially all Internet endpoints, including, but not limited to, any capabilities that are incidental to and enable the operation of the communications service, but excluding dial-up Internet access service.

(2) An "essential broadband Internet access project" shall comply with all labor requirements described in Section 21183.5.

(k)(1) "Essential education facility project" means the acquisition, construction, expansion, remodeling, renovation, improvement, furnishing, or equipping of an educational facility.

(2) An essential education facility project shall comply with all labor requirements described in Section 21183.5.

(o)(1) "Essential public safety project" means a first responder facility or a wildfire risk reduction project.

(2)(A) An "essential public safety project" shall comply with all labor requirements described in Section 21183.5.

(B) A wildfire risk reduction project limited to vegetation management, fuel reduction, creating or maintaining fuel breaks, or reducing fuel loading that is undertaken directly by a public agency using its own employees shall be deemed to comply with this paragraph if the public agency's employees working on the project are covered by a collective bargaining agreement or other state civil service laws that provide equivalent wage, training, and safety standards.

(q)(1) "Essential water project" means any project or action to construct, expand, repair, replace, improve, or augment any of the following: (A) a "public water system" as defined by subdivision (h) of Section 116275 of the Health and Safety Code; (B) a system that directly or indirectly provides water to a public water system; or (C) a system which is generally described and within the scope of the State's Water Resilience Portfolio.

(2) An "essential water project" shall comply with all labor requirements described in Section 21183.5.

(3) "An essential water project" does not include Delta conveyance facilities as defined in subdivision (f) of Section 79702 of the Water Code.

(s) "Feasible" means capable of being accomplished in a successful manner within a reasonable period of time, taking into account economic, environmental, legal, social, and technological factors.

(t)(1) "First responder facility" means all of the following:

(A) A fire station owned or operated by the State of California, a city, a county, a city and county, a joint powers authority, a Consulting Tribe, or a special district.

(B) A police station or sheriff's station owned or operated by a city, a county, a city and county, a joint powers authority, or a special district but excluding any portion thereof used as a jail or other detention facility.

(2) "First responder facility" does not include the following:

(A) Any facility owned, operated, or leased by the United States government.

(B) Any facility used as an immigration detention facility or a state prison.

(u) "Lead agency" means a lead agency as defined in Section 21067.

(v) "Local agency" means a public entity that is not a "state agency" as defined in this article.

(w) "Medical office building" means a building whose primary function is to provide office space for health care practitioners licensed, certified, registered, or otherwise authorized to practice pursuant to Division 2 of the Business and Professions Code.

(x) "Medical treatment facility" means all of the following: (1) a health facility as defined in Section 1250 of the Health and Safety Code; (2) a clinic as defined in Section 1200 of the Health and Safety Code; and (3) a medical office building.

(y)(1) "Mixed-use development" means a development consisting of residential and nonresidential uses that meets any of the following conditions:

(A) At least two-thirds of the new or converted square footage is designated for residential use.

(B) At least 50 percent of the new or converted square footage is designated for residential use and the project meets both of the following:

(i) The project includes at least 500 net new residential units.

(ii) No portion of the project is designated for use as a hotel, motel, bed and breakfast inn, or other transient lodging, except a portion of the project may be designated for use as a residential hotel, as defined in Section 50519 of the Health and Safety Code.

(C) At least 50 percent of the net new or converted square footage is designated for residential use, and the project meets all of the following:

(i) The project includes at least 500 net new residential units.

(ii) The project involves the demolition or conversion of at least 100,000 square feet of nonresidential use to residential use.

(iii) The project demolishes at least 50 percent of the existing nonresidential uses on the site.

(iv) No portion of the project is designated for use as a hotel, motel, bed and breakfast inn, or other transient lodging, except a portion of the project may be designated for use as a residential hotel, as defined in Section 50519 of the Health and Safety Code.

(2) For purposes of this subdivision, nonresidential uses shall not include any heavy industrial, extractive, port, refinery, or hazardous materials uses or designations.

(3) The minimum distance required between any nonresidential uses included in a mixed-use development and any existing off-site residential use shall be determined by state law.

(z) "Public agency" means a public agency as defined in Section 15379 of Title 14 of the California Code of Regulations; a responsible agency; a local agency; a state agency; a lead agency; a local agency formation commission; a city; a county; a city and county; a special district; a joint powers authority; or any other governmental authority created under state or local law whether statewide, local, or regional in character.

(bb) "Responsible Agency" means a responsible agency as defined in Section 15381 of Title 14 of the California Code of Regulations.

(cc) "State agency" means a state agency as defined in subdivision (a) of Section 8557 of the Government Code and any state body as defined in Section 11121 of the Government Code.

(dd) "State CEQA Guidelines" means Chapter 3 (commencing with Section 15000) of Division 6 of Title 14 of the California Code of Regulations.

(ee) "Substantial evidence" means enough relevant information and reasonable inferences from the available information that a fair argument can be made to support a conclusion, even though other conclusions might also be reached.

(ff) "Tribal cultural resource" includes any of the following:

(1) A site, feature, place, cultural landscape, or sacred place, including a sanctified cemetery, Indian cemetery, or burial area of a Consulting Tribe, or an object with cultural value to a Consulting Tribe that is any of the following:

(A) Included or eligible for inclusion in the California Register of Historical Resources or the National Register of Historic Places.

(B) Included in a local register of historical resources as defined in Section 5020.1.

(C) Identified by the Native American Heritage Commission as a sacred place pursuant to Section 5097.94 or 5097.96.

(D) Included in a tribal government register maintained by a Tribal Historic Preservation Officer approved by the Secretary of the Interior pursuant to Section 101 of the federal National Historic Preservation Act (54 U.S.C. Sec. 300101 et seq.).

(2) A cultural landscape that meets the criteria of paragraph (1) to the extent that the landscape is geographically defined in terms of the size and scope of the landscape.

(3) A historical resource described in Section 21084.1, a unique archaeological resource as defined in subdivision (g) of Section 21083.2, or a "nonunique archaeological resource" as defined in subdivision (h) of Section 21083.2 that conforms with the criteria of paragraph (1).

(gg) "Wildfire risk reduction project" means an activity that reduces wildfire risks to a residential or commercial structure, or both. A "wildfire risk reduction project" includes, but is not limited to, the following: replacing, hardening, or undergrounding electric utility lines, roads, and infrastructure; vegetation management; fuel reduction; home hardening; creating or maintaining fuel breaks and access roads; and reducing fuel loading.

ARTICLE 8. Construction of Chapter and General Provisions.

21029. Construction of Chapter.

21030. Statewide Concern.

21031. Statutory References.

21032. Severability.

The provisions of this chapter are severable. If any portion, section, subdivision, paragraph, subparagraph, clause, subclause, sentence, phrase, word, or application of this chapter is for any reason held to be invalid by a decision of any court of competent jurisdiction, that decision shall not affect the validity of the remaining portions of this chapter. The People of the State of California hereby declare that they would have adopted this chapter and each and every portion, section, subdivision, paragraph, subparagraph, clause, subclause, sentence, phrase, word, and application not declared invalid or unconstitutional without regard to whether any component of this chapter or application thereof would be subsequently declared invalid.

21033. Effective Date.

21034. Amendments.

SECTION 2. Conflicting Measures.

SECTION 3. Liberal Construction.

This Act shall be liberally construed to give effect to its intent and purposes.